About Aston Dane Office Locations Service & Support Past Events Careers News Partners

 

 

 

 
 

  

Cadbury Schweppes   Date (Aug 1998)

 

 

 

Aston Dane provides Critical Replacement Scheme for Crunchie production. 

 

 

When Cadbury needed to replace an elderly DCS system at its Keynsham plant it was important that the new system should be implemented as quickly as possible so as not to interrupt the supply of its Crunchie Bars.  The main production facility for Cadbury's Crunchie chocolate bars in the UK is situated at the old Fry's factory at Keynsham.  Although the plant used to produce the Crunchie bar is modern, the existing DCS control system was found to be in need of replacement, having been originally installed in 1981.

David Williams, Systems Engineer at Cadbury, explains why a new control system was required: "While the existing DCS had served us well for a number of years, we were starting to have problems with support, against a history of increasing downtime and pressure to continue to enhance the process performance through further automation.  Added to this, we had concerns over Y2K compatibility."

Cadbury approached Aston Dane plc for a possible solution.  Harry Booker, project manager at Aston Dane, takes up the story: "We have worked closely with Cadbury on many critical projects, however, the Crunchie project was exceptional in that the production downtime was continuously being squeezed due to high demand for the product.  Cadbury needed to remove the old equipment and install a new control system quickly, so as not to disrupt supplies."

Complex Process

Producing a Crunchie bar is a complex process.  The bar comprises two elements - the honeycombed centre and a milk chocolate coating.  The centre consists of sugar, glucose, syrup and flavourings, which are mixed to produce high temperature foam.  This mixture is fed onto a moving conveyor, where it is monitored to maintain a constant thickness.  As the mixture cools, it sets, and is then ready to be cut into individual pieces and coated in chocolate.  The time scale set for the new control system to be installed was 10 weeks.  In this time more than 3000 I/O needed to be replaced.

PLC-based Control

The new system is based around four Allen Bradley PLC5/80C controllers.  Installed within the same panels, and connecting via ControlNet™, is the Allen Bradley 1771 range of I/O, which provides signal interface to suit AC and DC applications.  Other communication methods employed at the plant are DeviceNet and Ethernet, which provides the backbone communication between the PLC and PC's running Rockwell Software RSView32.

Connected to the PLC's by DeviceNet, are 24 Allen Bradley drives to provide speed control of motors positioned all around the plant.  The whole process is monitored and controlled by two operators working the plant 24 hours a day.

Cadbury's Crunchie is one of the leading confectionery brands in the UK.  Careful planning and execution of the old Ferranti replacement was crucial to ensure that the famous Crunchie bars weren't compromised.

Home UtilitiesManufacturingServicesAsset ManagementProducts & SolutionsSite Map